Capital Projects and Equipment
for
FY2002-03 Budget

As a reinvestment in the infrastructure of the community's water system, we have planned the following capital improvement projects and equipment purchases during this fiscal year.

No.ProjectsEstimated Cost
1 Replace 8-inch main on Johnson from Connecticut to Colorado, on Colorado from Johnson to Lincoln, and on Connecticut from Johnson to Lincoln, 1,900 feet; retire 1,600 feet of 8-inch and 300 feet of 6-inch$ 90,000
2 Replace 8-inch on Johnson from Washingtion to Connecticut and on Connecticut from Johnson to Grant, 1,500 feet; retire 1,800 feet of 6-inch 78,000
3 Replace 6-inch and 2-inch on S. 7th from Anderson south, 450 feet; retire 450 feet of 2-inch 30,000
4 Install five sample sites inside city limits 4,000
5 Install blow off valves on 10 dead-end lines inside city limits 5,000
6 Replace 6-inch on Hall from First St. to railroad, 220 feet; retire 220 feet of 6-inch 12,000
7 Replace 2-inch on N. Tenth St. from Elrod south, 200 feet; retire 200 feet of 4-inch 7,500
8 Replace 2-inch on Marion St. from 16th St. south, 300 feet; retire 300 feet of 2-inch 8,500
9 Replace 8-inch on Third Ave. from "E" St. to "D" St., 350 feet; retire 350 feet of 2-inch 12,500
10 Replace Everest Avenue Reservoir; retire existing redwood tank 72,000
11 Construct Millingtion Pump Station 39,000
12 Replumb Telegraph Hill Pump Station 9,500
13 Replace four dunes well meters 13,600
14 Replace HVAC System at Pony Creek Water Treatment Plant 25,500
15 Install telemetry units at Terramar Pump Station and Reservoir 19,500
16 Install telemetry units at Flanagan Pump Station and Bay Park Millington 18,500
17 Paint Pony Creek Water Treatment Plant exterior 22,000
18 Paint Service Center Buildings exterior 57,000
19 Install five touch-read pads on meter vaults inside city limits 6,000
20 Continue distribution system mapping 35,000
21 Complete reference library shelving 1,500
22 Improve drive-up window 8,000
23 Design and construct office logo sign 1,000
  TOTAL ESTIMATED PROJECT COST$ 575,600
 Equipment Purchases
1 Air compressor $ 13,000
2 Construction pickup truck 15,000
3 Backhoe 60,000
4 To reserve for vehicle replacement 45,000
5 ASV power broom 4,800
6 Trash pumps (2) 2,500
7 Radios for equipment (2) 1,600
8 Pony Creek Water Treatment Plant filter-to-waste pump 9,000
9 Laboratory equipment 8,200
10 Treatment plant photocopier 2,700
11 Office computers (7) 12,400
  TOTAL ESTIMATED EQUIPMENT COST $ 174,200
  TOTAL ESTIMATED CAPITAL EXPENDITURES FY2002-03$ 749,800

Upper Pony Creek Dam
Water Expansion Project
Dunes Wellfield Expansion
Joe Ney Improvements


© 2001 Coos Bay-North Bend Water Board. All rights reserved.

This site was created by Web Development Students at
Southwestern Oregon Community College